A senior Iranian official said here on Wednesday that the construction of the gas platform of the 17th phase of South Pars gas field has been finished thanks to the nonstop endeavors of the domestic experts.
Managing Director of Mobin-Sazehgostar Company, Babak Abbaspour said the platform will be installed in South Pars gas field on Thursday.
He added construction of the platform saved the country 85 million dollars.
Once the 17th gas platform comes on stream, it will produce 500 million cubic meters of gas per day in South Pars gas field.
Abbaspour added Mobin-Sazehgostar Company has so far constructed several gas platforms in 15th and 16th phase of South Pars gas field.